Central Java 2x1000MW Coal Fire Power Plant Project
Detail Project :
- Project Owner : Mitsui Engineering & Shipbuilding Co Ltd
- Main Contractor : PT. Jurong Engineering Lestari
- Sub-Contractor : PT. SSA (Sepuluh Sumber Anugerah)
Project Location : Batang – Central Java - Scope of Work : Boiler Piping Fabrication & Field Installation, Tank Erection Works
Contract Date :
- Start Date : May 2018
- Finish Date : February 2020
–
Boiler Piping Works
Steel Structure Works
Tank Works